2025 · CBT 2
Afternoon
Electrician
ALP CBT-2 Previous Year Question 2025-05-02 Afternoon Shift Electrician
173 questions
120 min
173.0 marks
Your score
0 / 0
0 correct
0 wrong
0 skipped
111
Part B
+1.0M
-0.33M
What force effort will be required to push a load, initially at rest, of mass 500 g, so that at a distance of 20 m, its final velocity is 20 m/s? Assume no friction and �=10 m/s2g=10 m/s2.
112
Part B
+1.0M
-0.33M
Select the option that is correct regarding the following two statements labelled Assertion (A) and Reason (R). Assertion: The line voltage in a star-connected system is times the phase voltage. Reasoning: In a star connection, the line voltage is the vector sum of the phase voltages, resulting in a factor between them.
113
Part B
+1.0M
-0.33M
What is the recommended action if a DC motor produces excessive sparking at the brushes?
114
Part B
+1.0M
-0.33M
What is another name for CTS wiring?
115
Part B
+1.0M
-0.33M
Which of the following uses of wire gauge is INCORRECT?
116
Part B
+1.0M
-0.33M
Which of the following statements correctly describes the placement and purpose of orientation marks on a drawing sheet? 1. Orientation marks are placed at two opposite corners of the drawing sheet to indicate the correct orientation on the drawing board. 2. Orientation marks consist of arrow heads placed across the frame, with one at the shorter side and one at the longer side, coinciding with the centering marks. 3. One of the orientation marks always points towards the draughtsman, indicating the direction in which the drawing sheet should be placed. 4. Orientation marks are used to mark the midpoint of each side of the drawing sheet for accurate centering.
117
Part B
+1.0M
-0.33M
What determines the appropriate current rating of a fuse in a circuit?
118
Part B
+1.0M
-0.33M
A DC generator delivers a load current of 25 A at 200 V. If the generated EMF is 205 V, what is the armature resistance?
119
Part B
+1.0M
-0.33M
In which application is a Gate Turn-Off Thyristor (GTO) used?
120
Part B
+1.0M
-0.33M
When drawing a curved line of a specific length in an engineering drawing, which tool is most appropriate for ensuring accuracy?